79443 E&G Trailer Buffet First Lavatory Lavatory

Home Railway

Bo'ness & Kinneil Railway

Location History

North Yorkshire Moors RailwayApr 73-May 94

Current Location

Bo'ness & Kinneil Railway

 

Bo'ness & Kinneil RailwayMay 94-Present

Current Status

Under Restoration

 

 

Current Livery

BR Green

   

TRA Designation

2

   

Partner Vehicle(s)

None

 

 

Owner

Scottish Railway Preservation Society

 

 

Website

www.srps.org.uk

   

Record Last Updated

16 November 2024

   

Preservation Modifications
None

Preservation Information
79443 was withdrawn in October 1972 and preserved the following year on the North Yorkshire Moors Railway, not as a DMU vehicle in its own right but to provide volunteer facilities.

79443 was used as a static buffet at Goathland until its blue asbestos contamination resulted in its disposal in 1994.

Luckily the Scottish Railway Preservation Society saved the vehicle (which was now the only surviving Edinburgh & Glasgow vehicle), stripped it of asbestos whilst still at the North Yorkshire Moors Railway and moved it to their base at the Bo'ness & Kinneil Railway. Understandably, the SRPS had the full scale rebuild of its Class 126 3-car set to undertake, so 79443 was put into long term store to await its turn for restoration once resources were available.

In 2008, with the Class 126 3-car set completed, attention turned to 79443. Bodywork repairs were started, and it was decided to replace both the steel panels and framework as 79443 was in very poor condition.

2009 saw exploratory work done to the exterior of the vehicle, with parts removed for assessment. The restoration started in earnest the following year when the vehicle was moved undercover.

In 2010, the No1 (compartment end) was rebuilt. All fixtures and fittings such as the gangway rubbing plate, springs, timber, pass-comm equipment, water filler pipes, footsteps and so on were removed. The buffer beam was stripped of all but the buckeye coupling: jumpers, sockets, steps, buckeye chain, etc. The bodyside doors, one each side, were taken off and refurbished. Some careful sanding was done on the end to reveal the vehicle's overhaul history and the various lettering applied through the years. The window frames were also removed down one side of the vehicle. New metal was then welded on the inside of the length of the bodyside replaced, along the bottom edge, to form the new box section. New curved L-section pieces for the join between the end and roof were painstakingly made and fitted to No. 1 end. All new metal, plus adjacent panelling and framework, was then primed and covered with bitumen paint. Both gangway doors were fully restored during the summer.

The end of the roof was completed early in 2011. A new door pillar was fabricated and welded in at the corner of No. 1 end and corridor side. Metalwork above that door was repaired and new panels fitted. Rotten panels and framework were cut out from No. 1 end to approximately the centre of the vehicle on the unrestored side. All but the top few inches of the panels were replaced. Most of the new framework has been
welded on. All new body panels were cut to size and primed, then welded onto the bodyside. No. 1 end has been undercoated and black gloss was applied. No. 1 end passenger communication mechanism was assembled from refurbished and repaired parts from the vehicle and Mark 1 stock. The buffer beam was fully repainted with the cleaned-up jumper sockets and other bits painted.

In 2012, the gangway rubbing plate was refitted.Bodywork restoration took another leap forward, with almost all of the framework repaired on the corridor side with two-thirds of the bodyside replaced with new panelling. On the compartment side two-thirds of the framework repairs were compleed and just over half of the bodyside replaced. The underframe was descaled, primed and painted on approximately half the length of the vehicle. The first sections of new flooring were cut to size and welded in place, again starting from No. 1 end.

In 2013, the four windows fitted on the corridor side were completed with sliding lights and alloy trim. The four window openings on the other side were trimmed to exact size. Main and quarter lights were then fitted to the three compartment windows. All sliding lights not on the vehicle were re-painted ready for use. Welding repairs to the corridor side were almost completed, and primer applied to that side. New timber was fitted around one of the door openings on that side so that the first door could be installed. The recently fitted windows on the other side have been painted. Work on the new floor continued, with half the vehicle completed. Work to rebuild the partitions between the toilet, compartments and buffet area and was started. The first three partitions were cut to size and shape and successfully trial-fitted. All components needed to rebuild the compartments were gathered together to assess what was missing. Partitions and panelling were cleaned of many years of dirt, and sanding of interior woodwork for the compartments was underway. Painting of the interior of the roof was also completed.

2014 saw work continue to progress. Another partition was refurbished making four in total, and the welding completed on the corridor side. This side was then repainted inside and out into green undercoat. Coach letter holders were fitted to both sides of the No1 end. Sanding and repairing of corridor doors and interior woodwork continued.

2015-2017 saw several stints completing more and more of the bodyside fabrication which would be essential for providing the solid base required to build up the rest of the vehicle. Included in this was replacement of the steel flooring, upon which the wooden floors sit. At the same time, more components for the interiors were repaired and other minor jobs undertaken on the underframe.

In 2018 descaling of the underframe and solebar was undertaken with lots of cleaning and painting! Interior work included refitting more of the supporting timberwork to the passenger compartments. A summer work week in the goods shed (where welding and hot work is allowed) saw more fabrication work undertaken to some of the final sectiopns of corroded bodywork to be attended to. Further coats of bodyside paint were also applied during this period.

In 2019 work concentrated on the underframe again with propane tank boxes fully restored along which much heater ducting and other services "below deck". Inside the vehicle, preparations for the buffet area seating were being made and more door woodwork returned to place.

The 2020 winter work week saw the veneered toilet exterior walls fitted into place along with plywood flooring for it to sit on. This walling was common to mark 1 coaches and a salvaged example from a scrapped Corridor First was available to replace 79443's original which was lost in the asbestos stripping process. Progress was also made on sanding reclaimed compartment wall panelling (also salvaged, this time from scrapped Class 126 vehicles 59098 & 59099) destined for 79443's passenger compartments.

The next three years was spent further assembling the compartment walls with a focus on supporting timber work in the ceiling and walls.

The restoration of 79443 continues steadily.

Future Plans
To return the vehicle to operational service. Once completed, the vehicle will be interchangeable with 59404 between the two Class 126 powercars to represent a 3-car Class 126 containing a buffet car.

 

North side of 79443 - this is the last section of bodyside to go green - seen after its first coat of multuiple unit Green, 3/8/19. John Horne

   

No.2 end gangway rubbing plate after descaling and priming. The rotten lower section of body panel to the right has been cut out, 19/7/19. John Horne

   

The left-hand 'A' bank propane gas box after cleaning, with primer and grey paint applied, 25/5/19. John Horne

   

B Bank Bottle Boxes. Recently restored and repainted by John Horne, 1/3/19. Andrew McConnell

   

79443 back in the Museum workshop after the Summer Work Week 2018 in the Goods Shed, 29/7/18. John Horne

   

The second coat of Multiple Unit Green has just been applied from window 11 to door 3, 11/7/18. John Horne

   

79443 being extracted following its latest round of bodywork restoration, 6/3/17. Jim Ormiston

   

79443’s compartment side seen near the end of the 2017 Winter Woollies Work Week, 3/3/17. Andrew McConnell

   

79443 being shunted by the NBL shunter for a 2015 work week stint in the goods shed. The corner nearest the camera would be tackled in the 2018 Winter Woolies Work Week, 26/7/15. Andrew McConnell

   

The cycle starts again: major welding work on a new section of 79443 progresses, 1/8/14. John Horne

   

79443 goes green! Showing the fresh metal and excellent bodywork progress, 19/1/14. John Horne

   

Glass and sliders refitted to one of 79443's windows, 24/6/13. John Horne

   

Work continues on 79443 inside the shed at Bo'ness, 18/5/13. Chris Moxon

   

79443 viewed outside, its bodyside re-skin progressing well, 13/7/12. John Horne

   

79443 viewed outside, its bodyside re-skin progressing well, 13/7/12. John Horne

   

A much better corridor end seen on 79443 undergoing framework and steel skin replacement, 25/3/12. John Horne

   

79443 undergoing framework and steel skin replacement, 11/3/12. John Horne

   

79443 after the first section of bodywork had been completed. Stuart Mackay

   

79443 undergoing its first bodywork section repairs at Bo'ness, 22/8/11. Ian McLoughlin

   

79443 in the shed at Bo'ness under restoration, 16/6/10. David Beardmore

   

79943 inside the exhibition/restoration shed, 17/8/09. Bill Pugsley

   

After about a decade in store at Bo'ness restoration work has finally started on 79443, which needs structural repairs to all lower body pillars and completely reskinning. Present funding will only allow some of this work to be carried out, 3/9/07. Stuart Mackay

   

79443 remained on it's bogies, although when this 'composite' picture was taken the vehicle had not moved in nearly 20 years. The entrance was via the gangway door to the right, 21/5/91. Stuart Mackay

   

79443 at Goathland. Photography was difficult because of the location of the footbridge, 7/4/85. Malcolm Clements

   

79443 at Goathland. Photography was difficult because of the location of the footbridge, 7/4/85. Malcolm Clements

 

Interior

 

Newly-fitted floorboards in compartment 'B', 20/9/20. John Horne

   

The lavatory walls being assembled, 27/2/20. John Horne

   

The buffet area with tables and chairs roughly in place to give an idea of what this area will look like when restoration progresses, 15/9/19. John Horne

   

Compartment C with the new ceiling lamp bases fitted, 16/9/18. John Horne

   

Interior view of new body frame and panels at window 8, 29/7/18. John Horne

   

Painting of recently fitted key sheeting continues, 16/9/17. John Horne

   

New floor secion fitted to one end of 79443, 13/7/12. John Horne